Schedule: Past 7 Days Existing Talley 1. Completed the demolition of the Ballroom Storage Wall (the brick wall you could see from the exterior NE Corner) 2. Continued the 2nd floor 2-hour corridor wall 3. Completed the 3th floor abatement 4. Continued on the 4th-floor demo and abatement 5. Completed the lighted exit sign relocation in…
Read MoreSchedule: Past 7 Days Existing Talley 1. Installed the 2-hour fire separation wall in the Wolves’ Den restaurant and construction office 2. Removed asbestos and demolished the 2nd floor soffit 3. Removed asbestos and began demolition of the ballroom storage room 4. Completed the column wrap demolition for the temporary shoring (steadying) and stair on…