Lots of work inside and out on the project. As you can see on the webcam brickwork and glass has started to go up.
Schedule Update
Completion Date: December 29, 2014
- Note: Phase I Complete Late 2013
Actual Percentage Complete: 32% (Updated 3/26; Next update: 4/23)
Project News and Announcements
Close down preparations of the current facility have begun with the University Student Centers Administration moving to Witherspoon.
Artwork will begin to come down over Spring Holiday. The next 8 weeks will be busy as we continue the close down process and will do our
best to communicate potential disruptions. Stay tuned to Facebook and Twitter for updates.
New Activities or Major Updates during the Next 7 Days
Noise Level during work hours: Yellow. In general crews will continue a Monday-Saturday, 7am-6pm schedule.
Phase II
1. Final move out of units in Talley has begun and will continue through the rest of the semester.
Phase II
1. Construction begins June 1st, 2013
Progress Status Summary (updated 3/26; Next Update: 4/23)
1. 1st floor underslab MEP
- 95% complete, Anticipated next 30 days – 100% complete
2. Misc. Steel
- 95% complete, Anticipated next 30 days – 100% complete
3. Fireproofing – West side
- 98% complete, Anticipated next 30 days – 100% complete
4. Fireproofing – East side
- 98% complete, Anticipated next 30 days – 100% complete
5. Exterior Metal Stud Framing – East side
- 95% complete, Anticipated next 30 days – 100% complete
6. Curtain Wall Framing – East side
- 50% complete, Anticipated next 30 days – 85% complete
7. Curtain Wall Framing – West side
- 90% complete, Anticipated next 30 days – 95% complete
8. Interior Framing – East Side
- 40% complete, Anticipated next 30 days – 60% complete
9. Interior Framing – West Side
- 95% complete, Anticipated next 30 days – 95% complete
10. Roofing – East Side
- 90% complete, Anticipated next 30 days – 95% complete
11. Roofing – West Side
- 95% complete, , Anticipated next 30 days – 95% complete
12. Duct Work – West Side
- 95% complete, Anticipated next 30 days – 100% complete
13. Overhead Rough In – West Side
- 75% complete, Anticipated next 30 days – 90% complete
14. Brick Veneer – West Side
- 60% complete, Anticipated next 30 days – 90% complete
15. Drywall – West Side
- 0% complete, Anticipated next 30 days – 30% complete
Upcoming Construction Milestones:
- May 12, 2013 – Current Talley closes for construction
- June 2013 – Phase II construction starts
- Late 2013 – New Talley Phase I Opens
Stay connected with the Talley Project
Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: @NCSU_Talley
Facebook: Talley Student Center at North Carolina State University



