Noise Alert Level for Next 7 Days

YELLOW – Moderate noise and/or vibration. There may be occasional loud noise or heavier vibration, but should be mild overall.
Schedule: Past 7 Days

 

Schedule: Past 7 Days

Work around Jeter , Cates East and Reynolds
– Completed chilled water work along Jeter

Work around Cates East, Talley, Price and Alexander
– Backfilled steamline along Cates Avenue

Work around North Side of Talley (between Alexander and Reynolds)
– Resumed installation of new 8-inch water main near Alexander-
– Started the concrete stairs in the service drive at Alexander

Schedule: Next 7 Days

Note this is the schedule and work is subject to change
 
Work around Jeter, Cates East and Reynolds
– Complete chilled water installation at Jeter/Dunn Intersection. Dun Av evening closure at Jensen Dr. during evening/overnight hours Oct.17-21.

Work around Cates East, Talley, Price and Alexander
– Paving of Cates Avenue West
 
Work around North Side of Talley (between Alexander and Reynolds)
– Continue installation of new 8” water main near Alexander
– Complete concrete stairs in the service drive at Alexander
– Start the cast in place portion of STMH4