This report is intended to give the most recent information provided at the weekly construction meeting. Work is subject to change and more specific information may come from various departments regarding road closures, utility disruptions, etc.
Noise Alert Level for Next 7 Days
YELLOW – Moderate noise and/or vibration. There may be occasional loud noise or heavier vibration, but should be mild overall.
Schedule: Past 7 Days
Schedule: Past 7 Days
Work around Jeter , Cates East and Reynolds
– Completed chilled water work along Jeter
Work around Cates East, Talley, Price and Alexander
– Backfilled steamline along Cates Avenue
Work around North Side of Talley (between Alexander and Reynolds)
– Resumed installation of new 8-inch water main near Alexander-
– Started the concrete stairs in the service drive at Alexander
Schedule: Next 7 Days
Note this is the schedule and work is subject to change
Work around Jeter, Cates East and Reynolds
– Complete chilled water installation at Jeter/Dunn Intersection. Dun Av evening closure at Jensen Dr. during evening/overnight hours Oct.17-21.
Work around Cates East, Talley, Price and Alexander
– Paving of Cates Avenue West
Work around North Side of Talley (between Alexander and Reynolds)
– Continue installation of new 8” water main near Alexander
– Complete concrete stairs in the service drive at Alexander
– Start the cast in place portion of STMH4