Below is a summary of the previous week’s work and activity projected for the following week. Note that construction noise levels will increase significantly beginning February 21.
Schedule: Past 7 Days
1. Started the transformer for temporary construction power (by Wolf Plaza & Alexander)
Scaffolding starts to go up today (Friday)
Schedule: Next 7 Days
Starting Tuesday February 21 – Construction Noise will move from Yellow to RED
1. Complete transformer for temporary construction power
2. Start demolition and abatement activities on the North Side
Upcoming Work – More info to come:
Spring Break Steam Shutdown
Official communication will come from Facilities & Operations as well as Parking and Transportation.
Construction along Cates Avenue will commence February 27 to prepare for the steam shut down on Saturday March 3.
Expect one-lane traffic in front of Talley beginning February 27 through March 9. At night, the fence will be pulled back and two-lane traffic will resume. Contractors expect to be in the area until the end of the month, but traffic impacts should end on March 9 (weather permitting).
Stay connected with the Talley Project
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Facebook: www.facebook.com/TalleyStudentCenter