Below is a summary of the previous week’s work and activity projected for the following week.  Note that construction noise levels will increase significantly beginning February 21.

Schedule: Past 7 Days
1. Started the transformer for temporary construction power (by Wolf Plaza & Alexander)

Scaffolding starts to go up today (Friday)

Schedule: Next 7 Days

Starting Tuesday February 21  – Construction Noise will move from Yellow to RED 

1. Complete transformer for temporary construction power
2. Start demolition and abatement activities on the North Side

Upcoming Work – More info to come:

Spring Break Steam Shutdown

Official communication will come from Facilities & Operations as well as Parking and Transportation.

Construction along Cates Avenue will commence February 27 to prepare for the steam shut down on Saturday March 3.

Expect one-lane traffic in front of Talley beginning February 27 through March 9.  At night, the fence will be pulled back and two-lane traffic will resume.  Contractors expect to be in the area until the end of the month, but traffic impacts should end on March 9 (weather permitting).

Stay connected with the Talley Project 

Website: http://go.ncsu.edu/newtalley

Webcams: http://go.ncsu.edu/talleywebcam

Facebook: www.facebook.com/TalleyStudentCenter

Twitter: www.twitter.com/NCSU_Talley