Construction activity continues to increase. This includes activity at the Cates Avenue construction entrance. Please use caution when walking around the site and past construction entrances.
Schedule: Past 7 Days
Existing Talley
1. Completed the 2nd floor precast demolition
2. Completed the 2nd floor temporary corridor walls and ceiling
3. Continued the 3rd floor and 4th floor separation walls
4. Completed column shoring at northeast corner
– Blog post on the process: Digging a Little Deeper – Column Shoring and Extension
5. Poured temporary stair footings
North of Talley – West Side (Future site of Dock, Dining, Senate Chambers & Arts NC State)
1. Abated and removed steam piping
2. Continued grading and excavation
3. Continued temporary storm piping
North of Talley – East Side (Future site of Dining, Ballroom and Meeting Rooms)
1. staging for demolition
Other Areas
1. Completed the steam tie in at Cates Ave.
Schedule: Next 7 Days
Construction Noise will continue to be RED
Existing Talley
1. Remove scaffolding on the north side
2. Complete the 2nd floor corridor electrical work
3. Complete the 3rd and 4th floor separation walls
4. Start the North Stairwell Separation wall
North of Talley – West Side (Future site of Dock, Dining, Senate Chambers & Arts NC State)
1. Complete the precast demolition
2. Start the shoring and excavation west Talley elevation
North of Talley – East Side (Future site of Dining, Ballroom and Meeting Rooms)
1. Start the temporary stair erection on the northeast corner of Talley
2. Start the shoring and excavation at east Talley elevation
3. Staging for demolition
Other areas
1. Continue backfill at the Talley carriageway on Cates Ave
Upcoming Work – More info to come:
– Continue the Column shoring and extension work at the northeast corner of Talley
– Auger cast piles will start later this month
Stay connected with the Talley Project
To find out more about the current work and other upcoming work check out the two recent blog posts:
– **NEW** Digging a Little Deeper – Column Shoring and Extension (Blog Post – Apr 5th)
– Talley Construction Heats Up Spring 2012 (Blog Post – Feb 3rd)
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Facebook: www.facebook.com/TalleyStudentCenter
Twitter: www.twitter.com/NCSU_Talley