Talley Construction Update: May 10, 2012

|

Pedestrian Traffic
Fencing around the site should not change much over the summer and the pedestrian paths will continue to be open as they have been this semester. There will be significant construction traffic at the entrance by Alexander/Price and to create a safer environment we ask for your assistance. Please use the South side of Cates Avenue (between Tucker-Owen & FYC and Talley-Carmichael) so as to avoid crossing directly in front of the construction entrance gates.

Commencement Work & Summer Construction
Construction resumes normal work hours tomorrow (Friday 5/11) at 7am. Summer work hours will be primarily “sun up to sun down” though night work will be needed from time to time.

Schedule: Past 7 Days

Existing Talley
1. Began East (by Food Court) separatation walls

North of Talley – West Side
(Future site of Dock, Dining, Senate Chambers & Arts NC State)
1. Continued the concrete wall demolition outside of the Wolves Den
2. Continued site grading and shoring
3. Began the auger cast pile installation

North of Talley – East Side
(Future site of Dining, Ballroom and Meeting Rooms)
1. Continued site grading and shoring

Other Areas
1. Completed work and paved at Talley carriage way (Cates Ave.) at MH#81

Schedule: Next 7 Days
Construction Noise continues to be RED

Existing Talley
1. Complete the East (by Food Court) separation walls

North of Talley – West Side
(Future site of Dock, Dining, Senate Chambers & Arts NC State)
1. Continue concrete wall demolition outside of the Wolves Den
2. Continue the site grading and shoring
3. Continue the auger cast pile installation

North of Talley – East Side
(Future site of Dining, Ballroom and Meeting Rooms)
1. Continue the site grading and shoring

Other areas
1. Insulate steam piping in MH#61A

Stay connected with the Talley Project
To find out more about the current work and other upcoming work check out the recent blog post:
Talley Construction Heats Up Spring 2012 (Blog Post – Feb 3rd)

**NEW** Atrium Food Court Renovation Honored

Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: www.twitter.com/NCSU_Talley
Facebook: www.facebook.com/TalleyStudentCenter