Talley Construction Update – July 26, 2012

|

In addition to continuing the work you have seen, this week the project will be wrapping up the work on Cates Avenue (East and West) and begin the wall construction on the east side of the site. This week we have two pictures for you. The one above is an aerial photo from the middle of the month courtesy of our construction manager and the one below is a panoramic of the site from Alexander on Thursday July 26th and you can see the work on the elevated deck.

For more photos like us on Facebook or stay tuned to the live construction cameras.

Schedule: Past 7 Days (July 19 – July 25)
North of Talley – West Side
Future site of Dock, Dining, Senate Chambers & Arts NC State
1. Continued pile cap and grade beam installation
2. Continued concrete wall installation
3. Started the one-sided wall installation at Price Music Center
4. Continued the elevated deck activities

North of Talley – East Side
Future site of Dining, Ballroom and Meeting Rooms
1. Continued pile cap installation

Other Locations
1. Continued the east and west Cates duct bank installation

Schedule: Next 7 Days (July 26 – August 1)
Construction Noise will be Yellow

North of Talley – West Side
Future site of Dock, Dining, Senate Chambers & Arts NC State
1. Continue the concrete wall installation
2. Continue the one sided all construction at Price Music Center
3. Continue elevated deck activities

North of Talley – East Side
Future site of Dining, Ballroom and Meeting Rooms
1. Continue pile cap installation
2. Start the concrete wall installation
3. Start the 3rd & 4th floor glazing/precast demolition

Other
1. Complete the Cates Avenue East Ductbank by Reynolds
2. Complete the Cates Avenue West Ductbank by FYC & Student Health

**7/2 Blog Post: Update – Maps of Cates Avenue Duct Bank Work**

Stay connected with the Talley Project
October Talley Table Talk
Planning for our next table talk day is underway. See the below blog post for more information as an exciting new sketch of a signature New Talley space
**7/20 Blog Post: Update on Dining & Furniture selections

Fly Through!
See the virtual tour of the New Talley. This was initially shown in November and featured at the Talley Table Talk. We now have it uploaded for those who did not get a chance to see it. While the virtual tour is was based off of early construction documents and some things have changed, you can get a great sense of what it will be like to be in the New Talley.

Save the date – Steel Signing
Mark you calendar (or add us in the Guidebook app) and join us to sign your name on a piece of steel going into the New Talley. The Steel Signing will be during Wolfpack Welcome Week on Wednesday, August 15 from 11 a.m. – 1 p.m. (during Campus Crawl) and 7 – 9 p.m. (during Respect the Pack) at Wolf Plaza. Stay connected with Wolfpack welcome week on Twitter or on Facebook

Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: www.twitter.com/NCSU_Talley
Facebook: www.facebook.com/TalleyStudentCenter