A busy week ahead as steel begins to go up. The site will significantly change over the next week. Crews are busy packing up concrete forms and backfilling the site in anticipation of the crane arrival. Below is a picture from Tuesday September 12th from our Alexander Camera.

Schedule: Past 7 Days (September 6 – September 12)

North of Talley – West Side 

Future site of Dock, Dining, Senate Chambers & Arts NC State

1. Continued foundation waterproofing and backfill

2. Completed the 2nd floor elevated deck and pour

North of Talley – East Side 

Future site of Dining, Ballroom and Meeting Rooms

1. Continued pile cap installation

2. Continued the concrete foundation walls

3. Continued the wall bracing

4. Continued foundation waterproofing and backfill

Schedule: Next 7 Days (September 13 – September 19)

Noise will be Yellow through the weekend until Steel Starts on Monday at which point it will move to RED.

North of Talley – West Side 

Future site of Dock, Dining, Senate Chambers & Arts NC State

1. Continue the foundation waterproofing and backfill

2. Begin Structural Steel (Monday)

3. Strip formwork from area A slabs

North of Talley – East Side

Future site of Dining, Ballroom and Meeting Rooms

1. Continue pile cap installation

2. Complete wall bracing

3. Continue foundation waterproofing and backfill

Stay connected with the Talley Project 

Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: www.twitter.com/NCSU_Talley
Facebook: www.facebook.com/TalleyStudentCenter