Photo: View from Dunn toward North Main Entry November 27, 2012
Hope you had a great Thanksgiving break and final week of classes! Reflecting on our weekly construction updates, the schedule is beginning to look similar week to week with lots of activities continuing progress. Also in preparation for Phase I opening (late 2013) and Phase II construction starting (June 1st) the new format consolidates information and keeps us looking forward to the total completion of New Talley. We hope the new format keeps you informed of the week to week progress as well as the overall progress of the project!
Schedule Update
Contracted Completion Date: December 29, 2014
- Note: Phase I Complete Late 2013
Actual Percentage Complete: 17% (November 27th – updated monthly)
Project News and Announcements
1. Note from contractors about upcoming work and final exams: There are a some critical activities that need to take place on site during this time period, including the installation of the new electrical manhole in the service drive adjacent to Alexander Hall. We will make efforts to reduce the amount of heavy activities on the west side of the site, but some noisy activities will have to take place. We will make arrangements to not make any late night or early morning concrete pours during this time, but work can be expected to proceed from 7:00am through 6:00pm.
2. Earlier this month ARTS NC State and University Theatre sent out a 3-D memo regarding the closure of Stewart Theatre this December in order to prepare for Phase II construction.
New Activities or Major Updates during the Next 7 Days (updated weekly)
November 29 – December 5
Noise Level during work hours: Yellow
Phase I
1. Start the west side stairs
2. Start the 1st floor under slab utilities
Phase II
1. Stewart Theatre Closes for construction December 16, 2012
2. Construction begins June 1st, 2013
Progress Status Summary (November 27th – updated monthly)
1. Phase I waterproofing and backfill
- 95% complete, Anticipated next 30 days – 100% complete
2. Phase I West – Steel
- 100% complete
3. Phase I West – Fireproofing
- 75% complete, Anticipated next 30 days – 90% complete
4. Phase I West – Exterior Metal Stud Framing
- 5% complete, Anticipated next 30 days – 50% complete
5. Phase I West – Priority Wall Framing
- 100% complete
6. Phase I West – Duct Work
- 0% complete, Anticipated next 30 days – 5% complete
7. Misc. Steel
- 40% complete, Anticipated next 30 days – 80% complete
8. Phase I East – Foundations
- 100% complete
9. Phase I East – Steel
- 75% complete, Anticipated next 30 days – 100% complete
10. Phase I East – Slab on Deck Pours
- 67% complete, Anticipated next 30 days – 95% complete
11. Phase I East – Fireproofing
- 5% complete, Anticipated next 30 days – 40% complete
Upcoming Construction Milestones:
- February 2013 – Phase I building dried in
- May 12, 2013 – Current Talley closes for construction
- June 2013 – Phase II construction starts
- Late 2013 – New Talley Phase I Opens
Stay connected with the Talley Project
Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: @NCSU_Talley
Facebook: Talley Student Center at North Carolina State University
Photo: View from 4th floor Lounge westward over the future Stafford Commons