Talley Construction Update – January 3, 2013

|

Photo: View from Carroll Hall January 3, 2013

HAPPY NEW YEAR! Hope everyone had a great winter break. As you walk around the perimeter of the site you should notice some differences on site. Most notably is that the crane is gone, but also more of the exterior framing and skin has gone up. Inside the building suites, rooms and hallways are taking shape. Hopefully soon we will also have an announcement for the Late 2013 opening of New Talley. Stay tuned!

Schedule Update

Contracted Completion Date: December 29, 2014

  • Note: Phase I Complete Late 2013

Actual Percentage Complete: 22% (Updated 12/20; Next update: 1/22)

Project News and Announcements

1. Campus will be conducting a full-scale emergency exercise tomorrow (Friday, January 4th). This will impact traffic along Cates avenue. For more information see the NC State Bulletin article about the exercise.

New Activities or Major Updates during the Next 7 Days 

January 3 – January 9

Noise Level during work hours: Yellow. In general crews will continue a Monday-Saturday, 7am-6pm schedule.

Phase I

1. Start the West roofing installation

3. Start Reynold’s underground steam work

Phase II

1. Construction begins June 1st, 2013

Progress Status Summary (updated 11/27; Next Update: 1/22)

1. Phase I waterproofing and backfill

  • 95% complete, Anticipated next 30 days – 100% complete

2. Phase I West – Steel

  • 100% complete

3. Phase I West – Fireproofing

  • 75% complete, Anticipated next  30 days – 90% complete

4. Phase I West – Exterior Metal Stud Framing

  • 5% complete, Anticipated next  30 days – 50% complete

5. Phase I West – Priority Wall Framing

  • 100% complete

6. Phase I West – Duct Work

  • 0% complete, Anticipated next  30 days – 5% complete

7. Misc. Steel

  • 40% complete, Anticipated next  30 days – 80% complete

8. Phase I East – Foundations

  • 100% complete

9. Phase I East – Steel

  • 75% complete, Anticipated next 30 days – 100% complete

10. Phase I East – Slab on Deck Pours

  • 67% complete, Anticipated next 30 days – 95% complete

11. Phase I East – Fireproofing

  • 5% complete, Anticipated next 30 days – 40% complete

Upcoming Construction Milestones:

  • February 2013 – Phase I building dried in
  • May 12, 2013 – Current Talley closes for construction
  • June 2013 – Phase II construction starts
  • Late 2013 – New Talley Phase I Opens

Stay connected with the Talley Project 

Feedback or questions, email us talley-project@ncsu.edu

Website: http://go.ncsu.edu/newtalley

Webcams: http://go.ncsu.edu/talleywebcam

Twitter: @NCSU_Talley

Facebook: Talley Student Center at North Carolina State University