Photo: View from Carroll Hall January 3, 2013
HAPPY NEW YEAR! Hope everyone had a great winter break. As you walk around the perimeter of the site you should notice some differences on site. Most notably is that the crane is gone, but also more of the exterior framing and skin has gone up. Inside the building suites, rooms and hallways are taking shape. Hopefully soon we will also have an announcement for the Late 2013 opening of New Talley. Stay tuned!
Schedule Update
Contracted Completion Date: December 29, 2014
- Note: Phase I Complete Late 2013
Actual Percentage Complete: 22% (Updated 12/20; Next update: 1/22)
Project News and Announcements
1. Campus will be conducting a full-scale emergency exercise tomorrow (Friday, January 4th). This will impact traffic along Cates avenue. For more information see the NC State Bulletin article about the exercise.
New Activities or Major Updates during the Next 7 Days
January 3 – January 9
Noise Level during work hours: Yellow. In general crews will continue a Monday-Saturday, 7am-6pm schedule.
Phase I
1. Start the West roofing installation
3. Start Reynold’s underground steam work
Phase II
1. Construction begins June 1st, 2013
Progress Status Summary (updated 11/27; Next Update: 1/22)
1. Phase I waterproofing and backfill
- 95% complete, Anticipated next 30 days – 100% complete
2. Phase I West – Steel
- 100% complete
3. Phase I West – Fireproofing
- 75% complete, Anticipated next 30 days – 90% complete
4. Phase I West – Exterior Metal Stud Framing
- 5% complete, Anticipated next 30 days – 50% complete
5. Phase I West – Priority Wall Framing
- 100% complete
6. Phase I West – Duct Work
- 0% complete, Anticipated next 30 days – 5% complete
7. Misc. Steel
- 40% complete, Anticipated next 30 days – 80% complete
8. Phase I East – Foundations
- 100% complete
9. Phase I East – Steel
- 75% complete, Anticipated next 30 days – 100% complete
10. Phase I East – Slab on Deck Pours
- 67% complete, Anticipated next 30 days – 95% complete
11. Phase I East – Fireproofing
- 5% complete, Anticipated next 30 days – 40% complete
Upcoming Construction Milestones:
- February 2013 – Phase I building dried in
- May 12, 2013 – Current Talley closes for construction
- June 2013 – Phase II construction starts
- Late 2013 – New Talley Phase I Opens
Stay connected with the Talley Project
Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: @NCSU_Talley
Facebook: Talley Student Center at North Carolina State University