Talley Construction Update: October 13, 2011

|

This report is intended to give the most recent information provided at the weekly construction meeting. Work is subject to change and more specific information may come from various departments regarding road closures, utility disruptions, etc.

Noise Alert Level for Next 7 Days

YELLOW – Moderate noise and/or vibration. There may be occasional loud noise or heavier vibration, but should be mild overall.
Schedule: Past 7 Days

Schedule: Past 7 Days

Work around Jeter , Cates East and Reynolds
– Continued the chilled water work along Jeter
– Installed asphalt paving along Cates Avenue East

Work around Cates East, Talley, Price and Alexander
– Continued the steam installation along Cates Avenue
– Installed steam piping across Cates Avenue (in front of Talley)
– Complete the sanitary sewer to Price
– Installed asphalt paving along Cates Avenue West

Work around North Side of Talley (between Alexander and Reynolds)
– Installed storm sewer between STMH2 and STMH4
– Installed storm sewer installation between DI-5 and STMH4a

Schedule: Next 7 Days

Note this is the schedule and work is subject to change
 
Work around Jeter, Cates East and Reynolds
– Complete chilled water installation along Jeter and possibly start on Dunn Avenue
 
Work around Cates East, Talley, Price and Alexander
– Backfill steam line on Cates Avenue (Estimated date(s): Thursday 10/13 & Friday 10/14
– Paving of Cates Avenue West
 
Work around North Side of Talley (between Alexander and Reynolds)
– Resume Installation of new 8” water main near Alexander
– Install the concrete stairs in the service drive at Alexander
– Start the cast in place portion of STMH4