Walls started to go up this week. Here is a picture from the site as of 8am this morning where you can see two of the walls in progress.
To see more, check out the live feed.
Schedule: Next 7 Days (June 7 – June 13)
North of Talley – West Side
Future site of Dock, Dining, Senate Chambers & Arts NC State
1. Continued pile cap installation
2. Continued auger cast pile installation
3. Started concrete wall installation along Pe & P10 lines
North of Talley – East Side
Future site of Dining, Ballroom and Meeting Rooms
1. Started auger cast pile installation
Schedule: Next 7 Days (June 14 – June 20)
Construction Noise will be Yellow
North of Talley – West Side
Future site of Dock, Dining, Senate Chambers & Arts NC State
1. Continue the auger cast pile installation
2. Continue the concrete pile cap installation
3. Continue the concrete wall installation
North of Talley – East Side
Future site of Dining, Ballroom and Meeting Rooms
1. Continue the auger cast pile installation
Other
1. Start Alexander Hall repairs
Stay connected with the Talley Project
Fly Through!
See the virtual tour of the New Talley. This was initially shown in November and featured at the Talley Table Talk. We now have it uploaded for those who did not get a chance to see it. While the virtual tour is was based off of early construction documents and some things have changed, you can get a great sense of what it will be like to be in the New Talley.
Save the date – Steel Signing
Mark you calendar and join us to sign your name on a piece of steel going into the New Talley. The Steel Signing will be during Wolfpack Welcome Week on Wednesday, August 15 from 11 a.m. – 1 p.m. (during Campus Crawl) and 7 – 9 p.m. (during Respect the Pack) at Wolf Plaza.
Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: www.twitter.com/NCSU_Talley
Facebook: www.facebook.com/TalleyStudentCenter