It has been an exciting week on the site seeing over 1500 cubic yards of concrete poured. The first half of the 2nd floor elevated deck was poured overnight Saturday into Sunday and the rain managed to hold off. Crews started working on the formwork for the second half of this deck. Once that is complete Steel can begin, which is scheduled to start in mid September. Walls started to go up on the east side of the site with the corner formed up by the NE corner of the existing building. Below is a picture of the site from this morning where you can see all the major activities (mentioned below in the Next 7 days) underway.

We also have a variety of pictures updated on Facebook in the July and August Construction albums as well as the Aerials album.

Schedule: Past 7 Days (August 16 – August 22)

North of Talley – West Side 

Future site of Dock, Dining, Senate Chambers & Arts NC State

1. Continued the concrete wall installation

2. Continued foundation waterproofing

3. Placed the first elevated deck (Saturday Night into Sunday Morning)

4. Started forming the second elevated deck (Scheduled to pour September 7th & 8th)

North of Talley – East Side 

Future site of Dining, Ballroom and Meeting Rooms

1. Continued pile cap installation

2. Continued the concrete walls

3. Started the 3rd & 4th floor densglass installation

Schedule: Next 7 Days (August 23 – August 29)

Construction Noise will vary this week due to the major concrete pours.

Noise will be Yellow. For Alexander Residents Noise will be RED due to deck work activity next to the building.

North of Talley – West Side 

Future site of Dock, Dining, Senate Chambers & Arts NC State

1. Continue the waterproofing and backfill

2. Complete the mud mat for 2nd floor shoring support

3. Continue the elevated deck work (part 2 – closest to Alexander)

  • This portion of the deck is tentatively scheduled for Friday September 7th into Saturday September 8th. Too see more about upcoming work this fall see our blog post from August 2nd “Welcome to a new year“.

North of Talley – East Side

Future site of Dining, Ballroom and Meeting Rooms

1. Continue pile cap installation

2. Continue the concrete wall installation

3. Start wall bracing

4. Continue the 3rd & 4th floor densglass installation

Stay connected with the Talley Project 

**7/20 Blog Post: Update on Dining & Furniture selections

Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: www.twitter.com/NCSU_Talley
Facebook: www.facebook.com/TalleyStudentCenter