Talley Construction Update – September 20, 2012

|

As projected steel started this past week and progress is visible from hour to hour. The photo below from our Carroll Hall Camera shows the progress as of 8am this morning. You can see the start of the 3rd floor going up (service corridor and ARTS NC STATE suite). above it on the 4th floor will be the Senate Chamber and service corridor. To follow along with the progress, look at our live cams and Site photos on Facebook.

Schedule: Past 7 Days (September 13 – September 19)

North of Talley – West Side 

Future site of Dock, Dining, Senate Chambers & Arts NC State

1. Continued foundation waterproofing and backfill

2. Continued stripping formwork from slabs

3. Began structural steel

North of Talley – East Side 

Future site of Dining, Ballroom and Meeting Rooms

1. Continued pile cap installation

2. Continued the wall bracing

3. Continued foundation waterproofing and backfill

Schedule: Next 7 Days (September 20 – September 26)

Noise will be RED.

North of Talley – West Side 

Future site of Dock, Dining, Senate Chambers & Arts NC State

1. Continue the foundation waterproofing and backfill

2. Continue Structural Steel

3. Continue to strip slab formwork

North of Talley – East Side

Future site of Dining, Ballroom and Meeting Rooms

1. Continue pile cap installation

2. Complete foundation waterproofing and backfill

3. Demo slab edge outside C-Store

Stay connected with the Talley Project 

Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: www.twitter.com/NCSU_Talley
Facebook: www.facebook.com/TalleyStudentCenter **New Album: September Photos; Weekly Progress album updated**