Talley Construction Update – July 26, 2012

In addition to continuing the work you have seen, this week the project will be wrapping up the work on Cates Avenue (East and West)...

Talley Construction Update – July 20, 2012

Scaffolding is flying up as the crews begin work on the elevated deck, which will begin to close in “the hole” (as many of you...

Update on Dining & Furniture Selections

Thanks for all the inquiries about what the inside of Talley will look like. We have a variety of work groups in the process of...

Talley Construction Update – July 5, 2012

An exciting week on site this week! Crews could be spotted on site yesterday (July 4th) and by mid morning, columns were formed up. So...

Talley Construction Update – June 28, 2012

Walls continue to go up and this afternoon you can see columns start to go up in the loading dock and service area. Above is...

Talley Construction Update – June 21, 2012

The first wall was poured this past week and the second one is scheduled to be poured tomorrow (Friday). You can see walls three and...