This report is intended to give the most recent information provided at the weekly construction meeting. Work is subject to change and more specific information may come from various departments regarding road closures, utility disruptions, etc.
Noise Alert Level for Next 7 Days
YELLOW – Moderate noise and/or vibration. There may be occasional loud noise or heavier vibration, but should be mild overall.
Schedule: Past 7 Days
Schedule: Past 7 Days
Work around Jeter , Cates East and Reynolds
– Continued chilled water installation along Dunn Avenue
Work around Cates East, Talley, Price and Alexander
– Paved Cates Avenue West near Talley
– Continued waterline installation near Alexander Hall
-Completed concrete stairs to Alexander Hall
Work around North Side of Talley (between Alexander and Reynolds)
– Continued CIP base section Storm MH#4 (north of Talley)
Schedule: Next 7 Days
Note this is the schedule and work is subject to change
Work around Jeter, Cates East and Reynolds
– Continue chilled water installation along Dunn Avenue
Work around Cates East, Talley, Price and Alexander
– Complete CIP Base section of Storm MH#4 (north of Talley)
Work around North Side of Talley (between Alexander and Reynolds)
– Complete CIP Base section of Storm MH#4 (north of Talley)