Construction Update: November 10, 2011

|

Weekly Update:
Schedule: Past 7 Days
Work around Dunn, Jeter, Cates East & Reynolds
1. Tie in waterline at Dunn Ave and installed temporary hydrant
2. Installed telecommunications manhole at Cates Ave East.
Reviewed process for testing/flushing of chilled water piping.

Work around North Side of Talley (between Alexander and Reynolds)
1. Completed cast in place portion of Storm MH#4 (north of Talley)

 

Schedule: Next 7 Days
Note this is the schedule and work is subject to change
Work around Dunn, Jeter, Cates East & Reynolds
1. Begin chilled water piping test/flush procedure
2. Traffic shift on Dunn Ave (near Jeter)
– Crews will be working on the north (railroad track) side of the road. Dunn Avenue remains
open. No impact to Wolfline bus routes. We expect this traffic shift to last for approximately
two weeks.

Work around Cates East, Talley, Price & Alexander
1. Install Manhole 68 at Alexander Courtyard (Fri-Sun) – See details below.
2. Continue installation of storm sewer piping

Work around North Side of Talley (between Alexander and Reynolds)
1. Continue installation of cast in place Storm MH#4 (north of Talley)
2. Hydrostatic test of water line.

 

Big weekend item to note this week!

Excavation for Manhole 68 at Alexander Courtyard will begin at 9am Friday Nov. 11. Work will stop at 9pm and will resume at 9am Saturday Nov. 12th & Sunday Nov. 13th.

Work includes
Excavate and shore for new 8’x8’x7′ manhole
Excavate and shore for duct bank extension
Chip back existing concrete duct bank as necessary
Install new electrical manhole
Install duct bank to manhole (conduit and concrete)
Backfill excavation
Remove fence
Replace Mulch
Clean-up