Schedule: Past 7 Days

Work around Cates West, Talley, Price & Alexander
1. Installed manhole at Alexander Courtyard and connected duct bank
2. Completed installation of SMH#4
3. Started storm sewer piping between SHM#4 and SMH#4A
4. Continued site grading

Schedule: Next 7 Days
Note this is the schedule and work is subject to change

Work around Cates East, Talley, Price & Alexander
1. Complete storm sewer piping
2. Complete site grading (as far as possible until next phase of construction)
3. Complete testing and inspections of new water main

 Upcoming items to note:     
Official closures/info on the 2 items below would come from Transportation
1. Chilled Water Completion (12/1-12/9) around Jeter to include road closures and night work