Talley Construction Update: April 26, 2012

|

A couple general updates this week in addition to the past and next 7 days schedule.

Study Rooms Available in Talley
With the fire separation walls complete on the 3rd floor, the study rooms and lounge (formerly CSLEPS, Campus Activities and Parents & Families Services offices) have been reopened. There are 6 rooms plus lounge areas available for individual or group study on a first come first served basis. Building Hours are Sat-Sun 9am to 10pm and Mon-Fri 7:30am-10pm.

Egress Pattern Shift on North Side
With the opening of the new temporary egress corridor on the 2nd floor and completion of the fire separation walls on the north side, Emergency Egress to the North has changed. Signage will direct you to the proper location, however, please note these changes in your surroundings as you use existing Talley.

Reduced Construction Work Hours
Contractors will begin a reduced work schedule Monday, April 30th to Thursday, May 10th (last day of finals) for the heavy equipment. Work hours will be 9am-8pm and contractors will resume the 7am start Friday May 11th. After graduation and residence hall move out on May 12th, contractors will begin summer hours.

Work includes: Excavation and grading throughout the site, soil shoring (support), demolition, and auger cast piles (drilling and concrete pumping of 20 piles/day). Potential impacts and noise include: backup alarms and revving engines. Noise should not be any louder than what is currently experienced.

Schedule: Past 7 Days

Existing Talley
1. Completed the temporary separation walls
2. Opened the 2nd floor temporary corridor
3. Began the 1st floor (north side) glazing abatement and demolition

North of Talley – West Side
Future site of Dock, Dining, Senate Chambers & Arts NC State
1. Continued site grading and shoring
2. Installed the auger cast test pile (the big crane you see on site)

North of Talley – East Side
Future site of Dining, Ballroom and Meeting Rooms
1. Continued site grading and shoring

Other Areas
1. Steam line work at Cates Ave.

Schedule: Next 7 Days
Construction Noise will continue to be RED

Existing Talley
1. Start the north entrance (1st floor) separation walls.
2. Begin north entrance glazing abatement and demolition
3. Start the north entrance separation walls

North of Talley – West Side
Future site of Dock, Dining, Senate Chambers & Arts NC State
1. Begin concrete wall demolition outside of the Wolves Den
2. Continue the site grading and shoring
3. Conduct the auger cast pile test
4. Begin auger cast pile installation

North of Talley – East Side
Future site of Dining, Ballroom and Meeting Rooms
1. Continue the site grading and shoring

Other areas
1. Steam line work at Cates Ave.

Stay connected with the Talley Project
To find out more about the current work and other upcoming work check out the recent blog post:
Talley Construction Heats Up Spring 2012 (Blog Post – Feb 3rd)

Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: www.twitter.com/NCSU_Talley
Facebook: www.facebook.com/TalleyStudentCenter