While official move-in starts tomorrow, there is quite the buzz around campus! We are excited to welcome to the Fall semester! A lot has happened over the summer and a lot more is about to start. Read Welcome to a new year for details about what to expect this fall and to see pictures from the summer. Below is a picture of the site from Alexander Hall yesterday (8/8/12) afternoon.

Steel Signing August 15th – Mark you calendar and add us to your schedule in the Wolfpack Welcome Week Guidebook app.

Schedule: Past 7 Days (August 2 – August 8 )

North of Talley – West Side 

Future site of Dock, Dining, Senate Chambers & Arts NC State

1. Continued concrete wall installation

2. Continued the elevated deck activities

North of Talley – East Side 

Future site of Dining, Ballroom and Meeting Rooms

1. Continued pile cap installation

2. Started the concrete walls

3. Completed the 3rd & 4th floor glazing/precast demolition

Other Locations

1. Completed the West Cates Duct Bank installation

Schedule: Next 7 Days (August 9 – August 15)

Construction Noise will be Yellow

North of Talley – West Side 

Future site of Dock, Dining, Senate Chambers & Arts NC State

1. Continue the concrete wall installation

2. Continue elevated deck activities

3. Continue foundation waterproofing

North of Talley – East Side

Future site of Dining, Ballroom and Meeting Rooms

1. Continue pile cap installation

2. Continue the concrete wall installation