While official move-in starts tomorrow, there is quite the buzz around campus! We are excited to welcome to the Fall semester! A lot has happened over the summer and a lot more is about to start. Read Welcome to a new year for details about what to expect this fall and to see pictures from the summer. Below is a picture of the site from Alexander Hall yesterday (8/8/12) afternoon.
Steel Signing August 15th – Mark you calendar and add us to your schedule in the Wolfpack Welcome Week Guidebook app.
Schedule: Past 7 Days (August 2 – August 8 )
North of Talley – West Side
Future site of Dock, Dining, Senate Chambers & Arts NC State
1. Continued concrete wall installation
2. Continued the elevated deck activities
North of Talley – East Side
Future site of Dining, Ballroom and Meeting Rooms
1. Continued pile cap installation
2. Started the concrete walls
3. Completed the 3rd & 4th floor glazing/precast demolition
Other Locations
1. Completed the West Cates Duct Bank installation
Schedule: Next 7 Days (August 9 – August 15)
Construction Noise will be Yellow
North of Talley – West Side
Future site of Dock, Dining, Senate Chambers & Arts NC State
1. Continue the concrete wall installation
2. Continue elevated deck activities
3. Continue foundation waterproofing
North of Talley – East Side
Future site of Dining, Ballroom and Meeting Rooms
1. Continue pile cap installation
2. Continue the concrete wall installation
Stay connected with the Talley Project
October Talley Table Talk
**7/20 Blog Post: Update on Dining & Furniture selections