Talley Construction Update – December 13, 2012

|

Photo: View from Carroll Hall December 13, 2012

Another semester is in the books and the year is almost over! The site is buzzing with activity. Interior and exterior walls are going up, fireproofing continues, MEP (mechanical, electrical and plumbing) work  is happening, and the building is starting to take shape on the inside. Some rooms are framed in and in some cases you can look down a hallway. Remember back in August when the semester started and the first deck pour was about to begin? Check out the August 16th Update to see a picture of the site.

Schedule Update

Contracted Completion Date: December 29, 2014

  • Note: Phase I Complete Late 2013

Actual Percentage Complete: 17% (Next update: 12/20)

Project News and Announcements

1. There is a lot of work going on around campus during the break that impact traffic. This includes work on Cates Avenue with installation of a gas line for the New Talley and electrical shutdowns impacting the Cates/Morrill Traffic Light. For dates and other work on campus see NCSU Transportation’s Winter Construction Map.

2. Campus will be conducting a full-scale emergency exercise at the start of the new year, January 4th. This will impact traffic along Cates avenue. For more information see the NC State Bulletin article about the exercise.

New Activities or Major Updates during the Next 7 Days 

December 13 – December 19

Noise Level during work hours: Yellow

Phase I

1. Early Morning (4:30am) Concrete Pour Friday 12/14 for the 4th & 5th floor east side decks

2. Start the 3rd floor west Mechanical, Electrical and Plumbing rough-in

3. Start the east side stair installation

4. Test the new fire line

Phase II

1. Stewart Theatre Closes for construction December 16, 2012

2. Construction begins June 1st, 2013

Progress Status Summary (Next Update: 12/20)

1. Phase I waterproofing and backfill

  • 95% complete, Anticipated next 30 days – 100% complete

2. Phase I West – Steel

  • 100% complete

3. Phase I West – Fireproofing

  • 75% complete, Anticipated next  30 days – 90% complete

4. Phase I West – Exterior Metal Stud Framing

  • 5% complete, Anticipated next  30 days – 50% complete

5. Phase I West – Priority Wall Framing

  • 100% complete

6. Phase I West – Duct Work

  • 0% complete, Anticipated next  30 days – 5% complete

7. Misc. Steel

  • 40% complete, Anticipated next  30 days – 80% complete

8. Phase I East – Foundations

  • 100% complete

9. Phase I East – Steel

  • 75% complete, Anticipated next 30 days – 100% complete

10. Phase I East – Slab on Deck Pours

  • 67% complete, Anticipated next 30 days – 95% complete

11. Phase I East – Fireproofing

  • 5% complete, Anticipated next 30 days – 40% complete

Upcoming Construction Milestones:

  • February 2013 – Phase I building dried in
  • May 12, 2013 – Current Talley closes for construction
  • June 2013 – Phase II construction starts
  • Late 2013 – New Talley Phase I Opens

Stay connected with the Talley Project 

Feedback or questions, email us talley-project@ncsu.edu