Schedule: Past 7 Days
Existing Talley
1. Completed the 3rd and 4th floor separation walls
2. Completed the east side temporary stair erection (by Reynolds)
3. Cut the northeast building column
– Blog post on the process: Digging a Little Deeper – Column Shoring and Extension
4. Started the north stairwell separation walls
North of Talley – West Side (Future site of Dock, Dining, Senate Chambers & Arts NC State)
1. Continued site grading and shoring
2. Replaced storm manhole #1 and connected the piping
3. Mobilized the auger cast pile contractor
North of Talley – East Side (Future site of Dining, Ballroom and Meeting Rooms)
1. Continued site grading and shoring
Other Areas
1. Steam line work at Cates Ave.
Schedule: Next 7 Days
Construction Noise will continue to be RED
Existing Talley
1. Complete the temporary stair separation walls
2. Open the 2nd floor temporary corridor and stairs
– This is for temporary emergency exit from parts of the building.
3. Start the north entrance separation walls
– Note that as the north entrances (labeled emergency exit only) close, some emergency exits will change.
4. Begin ground floor glazing abatement and demolition
North of Talley – West Side (Future site of Dock, Dining, Senate Chambers & Arts NC State)
1. Begin concrete wall demolition outside of the Wolves Den
2. Continue the site grading and shoring
3. Install the auger cast test pile
North of Talley – East Side (Future site of Dining, Ballroom and Meeting Rooms)
1. Continue the site grading and shoring
Other areas
1. Steam line work at Cates Ave.
Stay connected with the Talley Project
To find out more about the current work and other upcoming work check out the recent blog post:
– Talley Construction Heats Up Spring 2012 (Blog Post – Feb 3rd)
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Facebook: www.facebook.com/TalleyStudentCenter
Twitter: www.twitter.com/NCSU_Talley