Talley Construction Update – September 20, 2012

As projected steel started this past week and progress is visible from hour to hour. The photo below from our Carroll Hall Camera shows the...

Talley Article – Aspire 2012 Vol. 2

Below are images of a recent feature in Aspire, A Cooper Carry E-Zine. Cooper Carry is the architecture firm heading up the interiors portion of New...

Steel starts Monday September 17th

If you have been following along with our weekly updates, we have been talking about a start date for steel erection. That day is around...

Talley Construction Update – September 6, 2012

What a week! Power was out today (Thursday) due to a non construction related issue. A big thanks to ALL the Student Centers Staff (and...

Talley Construction Update – August 30, 2012

Lots of progress this week with concrete walls and columns poured for the east half of the first floor as well as progress on the...

Talley Construction Update – August 23, 2012

It has been an exciting week on the site seeing over 1500 cubic yards of concrete poured. The first half of the 2nd floor elevated...