Schedule Update

Completion Date: December 29, 2014

  • Note: Phase I Complete Late 2013

Actual Percentage Complete: 25% (Updated 1/22; Next update: 2/26)

Project News and Announcements

None this week.

New Activities or Major Updates during the Next 7 Days 

January 31 – February 6

Noise Level during work hours: Yellow. In general crews will continue a Monday-Saturday, 7am-6pm schedule.

Phase I

1. Start west side masonry work

2. Prep, place and finish the 2nd floor east slab on grade

Phase II

1. Construction begins June 1st, 2013

Progress Status Summary (updated 1/22; Next Update: 2/26)

1. 1st floor underslab MEP

  • 45% complete, Anticipated next 30 days – 90% complete

2. Misc steel

  • 95% complete, Anticipated next 30 days – 98% complete

3. Fireproofing – West side

  • 95% complete, Anticipated next  30 days – 95% complete

4. Fireproofing – East side

  • 90% complete, Anticipated next  30 days – 95% complete

5.  Exterior Metal Stud Framing – West side

  • 100% complete

6.  Exterior Metal Stud Framing – East side

  • 50% complete, Anticipated next 30 days – 85% complete

7. Duct Work – West side

  • 20% complete, Anticipated next 30 days – 45% complete

8. Overhead Rough In – West side

  • 15% complete, Anticipated next  30 days – 30% complete

9. Roofing – West Side

  • 45% complete, Anticipated next  30 days – 90% complete

10. Interior Framing – West Side

  • 75% complete, , Anticipated next 30 days – 95% complete

11. Curtain Wall – West Side

  • 5% complete, Anticipated next 30 days – 50% complete

Upcoming Construction Milestones:

  • May 12, 2013 – Current Talley closes for construction
  • June 2013 – Phase II construction starts
  • Late 2013 – New Talley Phase I Opens

Stay connected with the Talley Project 

Feedback or questions, email us talley-project@ncsu.edu

Website: http://go.ncsu.edu/newtalley

Webcams: http://go.ncsu.edu/talleywebcam

Twitter: @NCSU_Talley

Facebook: Talley Student Center at North Carolina State University