Our apologies for not posting updates the past couple weeks. As you may have seen the building continues to change by the day. Curtain wall is starting to go up and masonry work is set to begin this week. If you walk by you can see the ballroom walls up and much more!
Schedule Update
Completion Date: December 29, 2014
- Note: Phase I Complete Late 2013
Actual Percentage Complete: 25% (Updated 1/22; Next update: 2/26)
Project News and Announcements
None this week.
New Activities or Major Updates during the Next 7 Days
January 31 – February 6
Noise Level during work hours: Yellow. In general crews will continue a Monday-Saturday, 7am-6pm schedule.
Phase I
1. Start west side masonry work
2. Prep, place and finish the 2nd floor east slab on grade
Phase II
1. Construction begins June 1st, 2013
Progress Status Summary (updated 1/22; Next Update: 2/26)
1. 1st floor underslab MEP
- 45% complete, Anticipated next 30 days – 90% complete
2. Misc steel
- 95% complete, Anticipated next 30 days – 98% complete
3. Fireproofing – West side
- 95% complete, Anticipated next 30 days – 95% complete
4. Fireproofing – East side
- 90% complete, Anticipated next 30 days – 95% complete
5. Exterior Metal Stud Framing – West side
- 100% complete
6. Exterior Metal Stud Framing – East side
- 50% complete, Anticipated next 30 days – 85% complete
7. Duct Work – West side
- 20% complete, Anticipated next 30 days – 45% complete
8. Overhead Rough In – West side
- 15% complete, Anticipated next 30 days – 30% complete
9. Roofing – West Side
- 45% complete, Anticipated next 30 days – 90% complete
10. Interior Framing – West Side
- 75% complete, , Anticipated next 30 days – 95% complete
11. Curtain Wall – West Side
- 5% complete, Anticipated next 30 days – 50% complete
Upcoming Construction Milestones:
- May 12, 2013 – Current Talley closes for construction
- June 2013 – Phase II construction starts
- Late 2013 – New Talley Phase I Opens
Stay connected with the Talley Project
Feedback or questions, email us talley-project@ncsu.edu
Website: http://go.ncsu.edu/newtalley
Webcams: http://go.ncsu.edu/talleywebcam
Twitter: @NCSU_Talley
Facebook: Talley Student Center at North Carolina State University