By StaffThe first wall was poured this past week and the second one is scheduled to be poured tomorrow (Friday). You can see walls three and... |News, Student Centers
By StaffProgress continues with over 400 piles installed and 20 pile caps poured! Here is a picture taken yesterday of the site, where you can see... |News, Student Centers
By StaffPedestrian Traffic Fencing around the site should not change much over the summer and the pedestrian paths will continue to be open as they have... |News, Student Centers
By StaffReduced Construction Work Hours Contractors will continue a reduced work schedule through Thursday, May 10th (last day of finals) for the heavy equipment. Work hours... |News, Student Centers
By StaffA couple general updates this week in addition to the past and next 7 days schedule. Study Rooms Available in Talley With the fire separation... |News, Student Centers
By StaffSchedule: Past 7 Days Existing Talley 1. Completed the 3rd and 4th floor separation walls 2. Completed the east side temporary stair erection (by Reynolds)... |News, Student Centers
By StaffConstruction activity continues to increase. This includes activity at the Cates Avenue construction entrance. Please use caution when walking around the site and past construction... |News
By Staff**Updated June 8, 2012 with Step 2 (cut column with excavated area and shoring) picture** This blog is a little different than our normal updates....