Talley Construction Update: May 3, 2012

Reduced Construction Work Hours Contractors will continue a reduced work schedule through Thursday, May 10th (last day of finals) for the heavy equipment. Work hours...

Talley Construction Update: November 18, 2011

Schedule: Past 7 Days Work around Cates West, Talley, Price & Alexander 1. Installed manhole at Alexander Courtyard and connected duct bank 2. Completed installation...

Construction Update: November 10, 2011

Weekly Update: Schedule: Past 7 Days Work around Dunn, Jeter, Cates East & Reynolds 1. Tie in waterline at Dunn Ave and installed temporary hydrant...